• Order press tools – June 2007 - Receive press tools – January 2008

  • Supplier appointment – May 2007 - March 2008

  • Factory modification – June 2007 – May 2008

  • Engine Programme – March 2007- June 2008 (This is the critical path and ambitious)

  • Commission and Pre- Production – May – mid 2008

  • Start of production – mid 2008

  • Significant production – end 2008